title: "NERSA Registration for Embedded Generation — A Step-by-Step Guide — SOLINK"
description: "Since Schedule 2 was amended in 2023, embedded generation projects up to any size no longer need a NERSA licence — but they still need to be registered. Here's the process, what's required, and the timelines to plan for."
lang: en
json-ld:
---

[![SOLINK](/assets/solink-logo-DvjvhsCl.png)](/)

[Home](/)[About](/about)

[Services](/services)

[Industries](/industries)

[Projects](/projects)[The Group](/group)

Platforms

[Resources](/resource-hub)[Careers](/careers)

[Get in touch](/contact)

[← Back to Resource Hub](/resource-hub)

# NERSA Registration for Embedded Generation — A Step-by-Step Guide

10 July 2026 · SOLINK

![NERSA Registration for Embedded Generation — A Step-by-Step Guide](/__l5e/assets-v1/310b3fda-11f7-40cb-9af4-06a4fc90d148/solink-renewable-energy-roadmap-business-south-africa.jpg)

The 2023 amendment to Schedule 2 of the Electricity Regulation Act removed the licensing threshold for embedded generation entirely. Projects of any size can now be built and operated without a NERSA generation licence — but they still need to be registered with NERSA. Registration is not optional, and the process is regularly misunderstood by both developers and end users. This guide walks through what a registration actually involves, what NERSA reviews, and how long realistic timelines look in 2026.

## **Registration vs Licensing — the Key Difference**

A licence is a formal authorisation to generate electricity, with public participation, hearings and typically a 12–18 month process. A registration is an administrative confirmation that a facility exists and meets grid-code and technical requirements. Under the current Schedule 2, all generation facilities that connect to the grid — regardless of whether they wheel, sell to a third party, or self-consume — must be registered. Only pure off-grid systems with no grid connection are exempt.

## **Step 1 — Confirm Your Grid Connection Path**

Before NERSA is even relevant, the project needs a grid connection agreement with Eskom or the relevant municipality. This is the single longest-lead item in most embedded generation projects and should be initiated as early as the feasibility stage. A cost estimate letter (CEL) or budget quote from the network operator is a prerequisite for registration.

## **Step 2 — Complete the Technical Design Package**

NERSA registration requires a completed technical design, signed off by a professional engineer registered with ECSA. This includes the single-line diagram, protection philosophy, grid-code compliance study (NRS 097-2 for LV, NRS 048 / SANS Grid Code for MV/HV), and either a factory acceptance test report or manufacturer certification for the inverters.

## **Step 3 — Submit the NERSA Registration Application**

The application is submitted through NERSA's online portal and includes the technical package above, proof of the grid connection agreement, environmental authorisations where applicable, land-use rights, company information and confirmation of the offtake arrangement. Registration fees are modest but scale with installed capacity.

## **Step 4 — NERSA Review**

NERSA's stated turnaround for registrations is 60 working days from a complete submission. In practice, most projects experience one or two rounds of clarification, so budgeting three to four months from submission to registration certificate is realistic. Incomplete applications are the biggest single source of delay — a well-prepared submission goes through significantly faster.

## **Step 5 — Commissioning and Grid Compliance Testing**

Once registered, the plant is commissioned and grid-compliance tested with the network operator. This typically involves witnessed inverter testing, protection verification, and — for larger systems — a formal grid code compliance certificate. Only after this can the plant legally export or wheel energy.

## **Common Pitfalls**

-   Assuming Schedule 2 removed all NERSA requirements — it removed licensing, not registration.
-   Starting NERSA registration before the grid connection agreement is signed.
-   Missing NRS 097-2 or grid code compliance documentation.
-   Failing to register a change in offtaker or capacity — NERSA registrations must be updated when material project parameters change.

## **Where SOLINK Adds Value**

SOLINK manages NERSA registration as part of our end-to-end project contracting and construction oversight services. We prepare the submission package, engage with NERSA on the client's behalf, and ensure the technical design meets both the registration and grid-code requirements — reducing the risk of costly re-work at commissioning. Get in touch if you are planning an embedded generation project and want the registration path de-risked from day one.

Keep reading

## Related articles

[View all →](/resource-hub)

[

![Eskom Tariff Increase 2026 — What It Means for Commercial & Industrial Businesses](/__l5e/assets-v1/9b12d9c1-3919-4132-a616-e32ebf28ac32/solink-traditional-electricity-rising-energy-costs-south-africa.jpg)

10 July 2026

### Eskom Tariff Increase 2026 — What It Means for Commercial & Industrial Businesses

NERSA's 2026 tariff decision has landed. Here's what changed, what it means for C&I electricity bills through the year, and which businesses are most exposed.



](/resource-hub/eskom-tariff-increase-2026-what-it-means-for-ci)[

![CAA Glint & Glare Compliance — What Every Solar Developer Needs to Know](/__l5e/assets-v1/dbf2eb43-31cb-4070-ab36-2fe9c9097d8c/glint-and-glare.jpg)

10 July 2026

### CAA Glint & Glare Compliance — What Every Solar Developer Needs to Know

The South African Civil Aviation Authority requires a glint & glare assessment for any solar project within specified proximity to an airport or airstrip. Here's when it's required, what the assessment involves, and how to avoid costly redesigns.



](/resource-hub/caa-glint-and-glare-compliance-requirements)[

![Solar PPAs Explained — What South African Businesses Need to Know](/__l5e/assets-v1/9ece5a00-c805-4f07-9671-2b0c64dd04c8/solar-panel-side.jpg)

10 July 2026

### Solar PPAs Explained — What South African Businesses Need to Know

A Power Purchase Agreement lets a business consume solar power without owning the system. Here's how PPAs work in South Africa, what the tariff structure looks like, and the five clauses that make or break the deal.



](/resource-hub/solar-ppa-explained-for-south-african-businesses)

Newsletter

## Renewable energy insights, straight to your inbox

Independent commentary on solar, BESS, wheeled energy and the South African electricity market.

Subscribe

I agree to receive marketing communications from SOLINK. You can unsubscribe at any time. 

SOLINK

South Africa's independent renewable energy consultant, project developer and facilitator — engineering bankable solar, BESS and wheeled energy solutions for commercial and industrial businesses.

[Start a project](/contact)

Services

-   [Overview](/services)
-   [Feasibility Studies](/services/feasibility-analysis)
-   [Battery Storage](/services/battery-storage)
-   [Wheeled Energy](/services/wheeled-energy)
-   [Glint & Glare](/services/glint-and-glare)

Company

-   [About](/about)
-   [The SOLINK Group](/group)
-   [Projects](/projects)
-   [Careers](/careers)
-   [Contact](/contact)
-   [LinkedIn](https://www.linkedin.com/company/solink-power-procurement/)
-   [Resource Hub](/resource-hub)

Platforms

-   [SOLINK Procurement](https://www.solinkplatform.co.za/login/)
-   [SOLTRAK](https://app.soltrak.co.za/)
-   [SOLINK Core](/core)

Contact

Cape Town

Black River Park, Fir St, Observatory, Cape Town, 7925

[021 300 0485](tel:+27213000485)

Johannesburg

3rd Floor, Unit T, 165 West St, Sandown, Sandton, 2031

[010 500 7675](tel:+27105007675)

[info@solink.co.za](mailto:info@solink.co.za)

© 2026 SOLINK. All rights reserved.· [Privacy Policy](/privacy-policy)

Independent renewable energy advisory · South Africa